Decide When To Open A Request

When finished pins, medals or keychains differ from the piece you signed, identify the affected lot before anything moves. Name the buyer or quality lead who can place stock on hold. Tell receiving and distribution which cartons to separate.

A supplier corrective action request asks the supplier to explain and prevent a defect. Open one when the same issue repeats, more stock could be affected or the risk warrants a formal response. Follow any requirements your order already sets.

Start from the receiving inspection record for bulk pins if you already checked the shipment. Carry its lot IDs, inspected quantities and findings into the request. Use the existing record to support the hold and the scope under review.

Check the accepted drawing, finish sample or packing requirement with the supplier. A known difference from an agreed reference gives both teams a finding they can reproduce. If the requirement is disputed, record that point and agree a comparison method.

Keep the immediate stock decision with the buyer who controls the order. Assign the supplier’s investigation to someone who can work across production and inspection. Ask both owners when they can provide the next confirmed facts.

Write The Request From Evidence

Two teal pins sit in individual trays beside tags, a magnifier and a lined inspection record.
Link the observed condition and approved reference to the actual affected lots before discussing cause.

Use one request ID across emails, photographs and stock records. Include the PO line, product revision, approved sample ID, shipment date and carton markings. Show the feature you checked and the observed difference in separate fields.

In this example, PO 6413 covers 1,200 corporate event lapel pins. Sample S12 shows teal enamel ending inside the raised logo border. The receiving team finds enamel across that border on four of 40 pins examined.

It records lot L21 and the two cartons from which those 40 came. It photographs each affected location next to the approved sample under comparable light. Those photos show what the team found and which lot it examined.

Keep an affected piece and approved sample separately tagged. Record where each one sits and who can release it for examination. Ask the supplier to confirm that its reference copy carries the same revision and sample ID.

Ask the supplier to acknowledge the request and name its response owner. Record when you need confirmed stock counts, cause evidence and a first verification lot. Use dates that reflect the order, available evidence and agreed review time.

Confirm The Containment Scope

Ask which other cartons share the same run, setup or relevant component batch. Request the production and shipping records that connect them. Where identifiers were mixed, keep the uncertain stock within the hold until the relationship is clear.

The example buyer puts all 720 L21 pins under review, including 180 already sent to the event office. The supplier traces 300 L22 pins to transit and 180 L23 pins to finished stock. An open reorder also has 150 pieces in production.

StockIllustrative Containment
540 At ReceivingBuyer isolates L21 cartons and records the inspection samples.
180 On SiteEvent office pauses handout and confirms its L21 count.
300 In TransitCarrier contact requests a hold or directs L22 to quarantine on delivery.
180 At SupplierWarehouse blocks L23 dispatch and labels the affected cartons.
150 In ProcessSupplier pauses related work and records it under the separate reorder.

The four finished groups account for all 1,200 pins on the original PO. Keep the additional 150 on the reorder line. Ask the supplier for a reason before including or clearing other orders that may share the same setup.

For each location, record the hold owner, confirmed count and next action. If some units have already been issued, record the count and who needs notification. Keep unconfirmed quantities visible until the location responds.

You may agree a documented sort when your event needs some stock quickly. Define what the sorter checks and how accepted pieces are marked. Record sorted counts separately from the original inspection and obtain the buyer’s release decision.

Test How The Defect Occurred And Escaped

Ask the supplier to show how the defect was made and how it passed final inspection. For an enamel spill, review the setup for the marked border and the instructions reviewers used. Request evidence for both findings.

Ask For Evidence Behind Each Cause

In the example, the supplier suspects a worn fixture let the pin shift during filling. Ask it to compare retained pieces and setup records from L21 with a stable setup. Confirm that the comparison recreates the observed spill.

The inspection card may show views of the face while leaving the border beside the lettering unmarked. Review that card with the actual pieces. Ask whether inspectors can distinguish the defect when the marked area is added to the check.

If the supplier suggests the enamel was damaged in transit, compare packed and retained pieces from the same run. Check the source of the photographs and whether the trays moved inside the carton. Record any open questions before approving changes.

Ask which lots and workstations used the suspected fixture or inspection card. A dated equipment record or lot traveler can help tighten the hold. A clear explanation should connect back to the specific border and affected run.

Approve The Change And Verification Plan

A tray of inspected pins and a separate hold bin sit beside a review sheet and a caliper.
Keep goods under hold until your agreed verification and stock release decisions are recorded.

Ask for a corrective change linked to each confirmed cause, with an owner, revision and effective lot. In the example, the supplier replaces the worn fixture and adds a setup check. Its reviewer also issues a marked border inspection reference.

Ask for the signed setup record from the first applicable production lot. Request the revised inspection reference and the first recorded check that uses it. Review those documents alongside the physical results from that lot.

Graco’s supplier corrective action procedure provides an example of a buyer checking later lots after a finding. Set your own inspection period and agreement with the supplier. Record which results your receiving or quality lead will verify.

GateIllustrative Evidence
Change In UseDated setup record identifies the replacement fixture and first applicable lot L24.
Check In UseReleased inspection reference marks the logo border. The L24 log shows recorded checks.
Stock ReleaseThe named buyer approves the lot against your order and the agreed inspection results.
Case ClosureEffectiveness evidence and affected stock decisions are complete and signed.

Agree which lots, quantities and records support your decision before another delivery leaves the supplier. Have the supplier identify older goods separately on its packing list. Let receiving know which shipment to check and which reference to use.

Review The Next Delivery Against The Plan

Match the next delivery to the supplier’s effective lot list before examining a piece. Check the carton mark, order line and approved reference. Keep goods packed before the change separate even when both groups arrive together.

Under the example plan, receiving checks L24 against S12 and confirms the new border record. Record how many pins were checked and what each check found. Complete the existing order checks as well as the added border comparison.

A valid L24 result can support releasing that lot within the buyer’s plan. The original L21 hold still needs its own disposition. For a divided shipment of custom marathon medals, keep the same link between each lot and destination.

If the original condition returns, extend the hold to affected quantities and send the supplier the new record. Ask whether the change applied to that lot and whether the original cause still fits. Update the buyer and release owner together.

Keep any outstanding evidence visible even after a shipment is released. In the example, the next two agreed lots also need a border check before the case can close. Record dates and who will review their results.

Close The Request And Resume Routine Checks

Close the request when the buyer can trace the finding, verified cause, implemented change and accepted follow-up results. Record how each held group was sorted, replaced, reworked or otherwise dispositioned. Reconcile the records with stock and shipment counts.

For PO 6413, file the setup record, revised border reference, L24 result and the later agreed results together. Have the buyer sign the case and notify receiving when heightened checks can end. Keep the issue ID on the order history.

Record which tooling, finish and revision the next purchasing team should use. The custom metal merchandise reorder guide helps carry that reference into another PO. Keep your corrective action evidence retrievable if the same symptom appears again.

  • Name who signs the effectiveness decision and when regular receiving checks resume.
  • Attach a disposition or specific follow-up owner to every affected stock group.
  • Record the revised control and first production lot on the order history.
  • Give receiving a way to reopen the request if the finding returns.

Frequently Asked Questions

Can One Request Cover Several Purchase Orders?

Yes, when the evidence connects the same problem to a shared process or component. List each order, lot and quantity separately. Keep each stock decision tied to the affected order.

What If The Supplier Cannot Share Its Full Process Record?

Ask for a dated extract, a witnessed demonstration or an inspection record that shows the relevant control. Keep the document reference and revision. Your quality lead can then decide whether it answers the specific question.

What If Our Order Drawing Changes During The Investigation?

Check the original delivery against the revision the supplier accepted for that order. Record the new drawing and its effective lot separately. Ask which inspection record will apply to the replacement order.

Can We Accept Replacements While The Request Remains Open?

Record the replacement lot and the evidence supporting its release. Keep the corrective action open until your agreed effectiveness checks are complete. Tell receiving which controls still apply.

What If Another Production Run Is Months Away?

Review current containment and implementation records now. Set a follow-up trigger for the first new run and name the reviewer. Keep the effectiveness check recorded as pending until the agreed evidence exists.

How Do We Handle A Possible Transit Defect?

Preserve the carton condition and packing records with the affected samples. Compare pieces from different cartons and request the supplier’s predispatch evidence. Confirm where the damage occurred before assigning corrective work.