Set The First Article Gate

Identify the order line and version that need a first article inspection. Set the point at which your supplier needs buyer approval to proceed.

Ask for a specimen made with the intended production tools, material and finishing route. Record any stage that must be reviewed before final assembly.

A supplier might send a model early for design review. Keep that review distinct from your check of the first medal made by the intended process.

Name who supplies the sample, who records the results and who can release the run. Put those responsibilities and the review date on the order.

Boeing’s supplier planning guide shows how an industrial buyer assigns responsibility and inspection methods. Apply the requirements agreed for your own medal order.

If you need several versions, state which versions require separate evidence. Ask the supplier to show how it will identify the approved version during production.

Confirm when tooling trials may start and when the supplier needs a release for the bulk run. Put any allowed trial quantity beside that instruction.

Allow time for the buyer’s review, a revised submission and the supplier’s response. Record whether the agreed schedule starts before or after first article approval.

Turn The Drawing Into A Feature List

Start from the signed drawing revision and the purchase order line. Give each dimension, note or appearance check a number the supplier can cite.

Mark where to measure overall width, body thickness and usable slot width. Use the drawing to show where each measurement begins and ends.

Front and back of one runner medal beside a caliper and ruler, with close views of the edge, mount and reverse.
Number the important features on the front, reverse and edge so the report can identify each check.

If thickness matters at a flat rim, point to that location on the drawing. On a sculpted design, identify the relieved area separately.

For a ribbon slot, identify its clear opening after the agreed finish. Compare the fit against the actual sewn ribbon from your approved ribbon specification.

Specify which checks use numbers and which use an approved reference or observation. Give a usable criterion for finish, wording, orientation and any required assembly.

Ask the supplier to raise unclear or conflicting requirements before inspecting. Have the drawing owner issue a written clarification that the report can cite.

Mark the reverse orientation against the front and identify any reference location for engraved or formed text. Use the exact wording and version on the drawing.

Identify The Production Specimen

Tie the submitted medal to the part number, revision and production route. Record the sample ID on its packaging and in every photograph used as evidence.

Ask which tool, process and finish produced the sample. Include a tool or cavity identifier where your agreed inspection scope needs one.

If an alternate process makes the prototype, record that fact in the submission. Request representative evidence for any feature that depends on the intended process.

Give the specimen and any retained duplicate unique IDs. If you approve a duplicate as the reference, record which parts and report results it represents.

Check that the front, reverse and attachment in the report belong to the same submitted configuration. Ask the supplier to identify any temporarily fitted components.

State how the supplier should handle a revised sample. Keep its report and photographs separate from the previous submission so the approval trail stays readable.

Agree the number and selection of specimens before the supplier starts the inspection. Ask which versions or tools the selection represents and how that was verified.

If the factory runs parts through more than one finishing route, label each route in the request. Ask the supplier to distinguish those parts in its report.

Measure The Required Features

Agree how each dimension will be checked and recorded. Ask the supplier to use suitable measuring equipment and record its identification where the plan requires it.

Keep the drawing units in the report and record actual values alongside their limits. Highlight any conversion the supplier had to make before evaluating a result.

Confirm the specimen is at the correct production stage for the planned checks. A finish, added coating or final assembly may affect the feature you measure.

Ask the inspector to record where the tool contacted the part when the location affects the result. Include a marked photo for hard-to-find areas.

Treat appearance and fit as separate checks if the drawing specifies both. A medal can look correct and still need a slot or assembly review.

Save the approved reference beside each qualitative judgement. A photo can identify the checked area and support comparison with the criterion shown on the order.

Agree how the inspector should report a reading near its limit. Check whether the instrument can resolve the dimension at the precision your drawing requests.

Read The First Article Inspection Report

Match the first article inspection report to the approved drawing and sample ID before reviewing the results. Confirm that every required feature has a recorded outcome.

MACOM’s supplier quality manual gives a buyer example of first article reports with measurements and test evidence. Use the scope specified for your order.

Ask for an explanation if the report gives only a pass mark for a measured dimension. Confirm which actual result supports the decision.

Suppose a buyer checks a custom medal made on the planned tooling after finishing. The following limits apply to one fictional drawing revision.

FeatureExample Report Entry
Body Diameter64.60 to 65.40 mm allowed. Actual 65.10 mm. Accept.
Body Thickness5.20 to 5.60 mm at the marked rim. Actual 5.38 mm. Accept.
Clear Ribbon Slot21.80 to 22.20 mm allowed. Actual 21.72 mm. Hold.
Reverse MarkMatches approved revision C at the marked location. Accept.

The slot is 0.08 mm below the agreed minimum in this example. Keep the first article on hold while the supplier explains the result.

Ask the supplier to record the sample ID, the measured location and the relevant measurement method. The drawing owner needs those details to decide what happens next.

For visual checks, look for a reference identifier and an observation for the marked area. If a required feature was skipped, record it as an approval hold.

Record The Approval Or Hold

Keep the disposition with the report, sample ID and drawing revision. Record the date, approving person and the versions the decision covers.

Two matching brass medals in separate sage and coral trays beside a gloved hand, magnifier and lined report.
Keep a held sample separate and preserve its report until the named buyer records a decision.

If the supplier confirms a correctable cause, request a new representative specimen after correction. Record the original result and the checks required on the new sample.

Ask whether the correction affects other specified features. Give the supplier a written recheck scope that includes affected dimensions, appearance and fit where relevant.

If a buyer can approve a deviation, require written authorization for the exact feature, quantity and scope. Link any deviation to the approved drawing and sample.

For a completed approval, state which work is released and when. Keep any other finishes, versions or processes awaiting their own evidence on hold.

In the slot example, suppose the supplier corrects the opening and measures 22.04 mm on a new specimen. Check the approved scope before accepting that result.

If the slot work touched the finish or contact edge, review those features on the replacement. Link the new inspection and its disposition to the held report.

Carry The Result Into Production

Issue the signed report and sample reference to each person who uses them. Give the supplier one active set of approved drawing and inspection instructions.

Ask the supplier which changes trigger another first article review. Agree how it will notify you if tooling, material, finish or manufacturing location changes.

  • Record the approved drawing revision and physical sample ID on the order.
  • Link the release to the report, signed disposition and any limits.
  • Tell receiving which reference to use when the shipment arrives.
  • Keep any open corrective actions visible with an owner and due date.

Set the checks for later deliveries separately from the first article decision. Use the medal carton check-in guide to hand off the approved identifiers to receiving.

Keep the final report and any revised evidence available for a repeat order. Ask your team to check that the approved configuration still applies before using it.

Frequently Asked Questions

Can We Review The First Article Remotely?

Agree which features the buyer can verify with a live view or clear images. Require actual readings where dimensions matter. Keep a route for examining the physical specimen when finish or fit requires it.

Can One Report Cover Several Tool Cavities?

Agree how the supplier will identify pieces made in each cavity. Ask which cavities need their own evidence for features the tooling can affect. Tie any shared report to your written inspection scope.

What If The Supplier Proposes A Different Measurement Tool?

Ask the supplier to record its proposed method and explain whether the tool can resolve the required dimension. Have the technical owner approve the approach before treating it as evidence.

Does A New Finish Always Need A Full Inspection?

Ask which features the finish change might affect and check your approved requirements. Your buyer can specify a targeted review if permitted. Record what is covered and which approvals still apply.

Can A Signed Report Be Used For Several Destinations?

Confirm that the destinations will receive the same approved version and configuration. Provide each receiving team with the same report and identifiers. Document any site-specific pack or labeling differences separately.